Legislation · Chile
Chile implements affidavits to streamline construction permits
DLA Piper | On February 23, 2026, Chile published Supreme Decree No. 10/2025 (Decree) in the government’s Official Gazette, amending the General Urban Planning and Construction Ordinance (OGUC) to enable alternatives to permits or authorizations for the execution of construction works.

DLA Piper | On February 23, 2026, Chile published Supreme Decree No. 10/2025 (Decree) in the government’s Official Gazette, amending the General Urban Planning and Construction Ordinance (OGUC) to enable alternatives to permits or authorizations for the execution of construction works. In addition, the amendment fulfills the requirement established in Law No. 21,718 on the streamlining of construction permits, published on November 29, 2024.
The Decree introduces significant modifications to the OGUC, such as by allowing, in certain cases, the execution of certain works through the filing of affidavits and the replacement of the Municipal Building Departments with a system of widened professional responsibility and subsequent oversight. These changes aim to reduce timelines and administrative burdens on the Municipal Building Departments.
In this alert, we highlight the implementation of affidavits established by the Decree.
Context and objectives of Law No. 21,718
Law No. 21,718 on the streamlining of construction permits aims to simplify administrative construction procedures and reduce timelines and burdens for property owners. The amendment to Article 116 of the General Law of Urbanism and Construction (LGUC) altered the existing permit system, empowering the OGUC to establish exceptions in which the development of works without a traditional building permit is enabled, allowing for the categorization of projects according to their complexity.
Alternative enabling techniques: Affidavits
Alternative enabling techniques are instruments that, in the cases indicated by law and the OGUC, enable the execution of construction works without requiring authorization or permit from the Municipal Building Department. Among these techniques is the submission and filing of an affidavit, which corresponds to a document signed by the property owner, the architect, and other intervening professionals, who declare and certify, under their responsibility, that the works comply with urban planning regulations and all applicable provisions.
Types of affidavits
The new regulation establishes the following types of affidavits:
- Affidavit for commencement of works: Enables the beginning of the execution of works after payment of the corresponding municipal fees.
- Affidavit for completion of execution: Must be submitted once the works are finished and is equivalent, for purposes of the responsibilities referred to in Article 18 of the LGUC, to the final reception of the work.